Content

 

1.    Basic Project Information. 6

2.    Noise Monitoring. 12

3.    Waste management 17

4.    Landfill gas monitoring. 18

5.    Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions  22

6.    EM&A Site Inspection. 24

7.    Future Key Issues. 25

8.    Conclusion and Recommendations. 26

 

Appendix A

Construction Programme

Appendix B

Summary of Implementation Status of Environmental Mitigation

Appendix C

Impact Monitoring Schedule of the Reporting Month (Blank)

Appendix D

Noise Monitoring Equipment Calibration Certificate (Blank)

Appendix E

Event/Action Plan for Noise Exceedance

Appendix F

Noise Monitoring Data (Blank)

Appendix G

Waste Flow Table

Appendix H

Landfill Gas Monitoring Equipment Calibration Certificate

Appendix I

Landfill Gas Monitoring Data

Appendix J

Complaint Log and Regulatory Compliance Proforma

Appendix K

Site Inspection Proforma

Appendix L

Proactive Environmental Protection Proforma

Appendix M

Impact Monitoring Schedule of Next Reporting Month (Blank)

 

 


Executive Summary

Introduction

A1.       Penta-Ocean - Concentric Joint Venture (POCJV) is contracted to carry out the Mainlaying in Tseung Kwan O under Contract No. 13/WSD/16 (hereinafter known as “the Project”).

A2.       In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Project, EM&A works should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Project.

A3.       This is the 3rd Monthly EM&A Report, prepared by ASCL, for the Project summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O (TKO) during the reporting period from 1 October 2018 to 31 October 2018.

A4.       The EM&A programme for this contract has covered environmental monitoring on construction noise level at selected NSRs and Contractor’s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, Landscape and Visual and Ecology.

Summary of Main Works Undertaken & Key Mitigation Measures Implemented

A5.       Key works carried out in this reporting period for the Project included the following:

Location

Works Conducted in the reporting month

Portion A, B, C & D of the Project Site

·             Initial joint survey with WSD

Portion F & G of the Project Site

·             Erection of fencing and gates

·             Site accommodation erection and internal fitting out

Portion J of the Project Site

·             Continue utilities checking and detection before road works.

·             Ground Investigation works at 17 no. of trial pits done at Wan Po Road (CH. A3+50, 5+30, 13+70, 15+40, 16+30, 18+50, 19+00, 22+70, 41+10), Po Hong Road (CH. A44+80, 51+80, 63+60 and 69+60), Ling Hong Road (CH. A55+50 and 56+00), Po Shun Road (CH.A 54+30) and Wan Po Road (CH. A37+25).

·             3 nos. of work fronts implemented as scheduled for the open-trench between CH. A0+00 to 13+70

 

A6.       The major environmental impacts brought by the above construction works include:

·            Construction dust and noise generation from erection of fencing and gates, ground investigation works and trial pits works

·            Waste generation from construction activities

A7.       The key environmental mitigation measures implemented for the Project in this reporting period associated with the above construction works include:

·            Dust suppression by regular wetting and water spraying for the erection of fencing and gates, trial pits works

·            Reduction of noise from equipment and machinery on-site

·            Sorting and storage of general refuse and construction waste

Summary of Exceedance & Investigation & Follow-up

A8.       No noise monitoring was conducted during the reporting period due to the over distant monitoring station from the works location. No project-related exceedance of the Action Level was recorded during the reporting period.

Complaint Handling and Prosecution

A9.       No project-related environmental complaint was received during the reporting period.

A10.    Neither notifications of summons nor prosecution was received for the Project.

Reporting Change

A11.    There were no changes to be reported that may affect the on-going EM&A programme.

Summary of Upcoming Key Issues and Key Mitigation Measures

A12.    Key works anticipated in the November 2018( the next reporting month)  for the Project will include the following:

Location

Works Conducted in the next reporting month

Portion J of the Project Site

·             Trial pit works to check with the existing utilities

·             Trial pits excavation at HK Velodrome

·             3 nos. of open-trench between CH. A0+00 to 13+70.

A13.    The major environmental impacts brought by the above construction works will include:

·            Construction dust and noise generation from trial pit works and open-trench

·            Waste generation from construction activities

A14.    The key environmental mitigation measures for the Project in the coming reporting period associated with the above construction works will include:

·            Dust suppression by regular wetting and water spraying for trial pit works

·            Reduction of noise from equipment and machinery on-site

·            Sorting and storage of general refuse and construction waste

1.         Basic Project Information

1.1      Background

1.1.1      The proposed Desalination Plant at Tseung Kwan O (DPTKO) will produce potable water with an initial capacity of 135 million liters per day (MLD), expandable to an ultimate capacity of 270 MLD in the future to provide a secure and alternative fresh water resource complying with the World Health Organization (WHO) standards.  The plant will adopt the Seawater Reverse Osmosis (SWRO) technology, which dominates the market due to its reliability and progressive reduction in cost as the technology advances.

1.1.2      Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Variation of Environmental Permit (No. EP-503/2015/A) to Water Supplies Department (WSD) for the Project on 26 January 2018.

1.1.3      The scope of the Contract may be considered in brief, to consist of the laying of about 10km long 1200mm diameter fresh water mains and the associated works along the alignment of the Project as shown with the overall view in Figure 1.1.



Figure 1.1 Overview of Mainlaying in TKO


1.2      The Reporting Scope

1.2.1      This is the 3rd Monthly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 October 2018 to 31 October 2018.

1.3      Project Organization

1.3.1      The Project Organization structure for Construction Phase is presented in Figure 1.2.

                                                                      

Figure 1.2 Project Organization Chart

1.3.2      Contact details of the key personnel are presented in Table 1.1 below:

Table 1.1 Contact Details of Key Personnel

Party

Position

Name

Telephone no.

Penta-Ocean -Concentric Joint Venture

Environmental Officer

Tony Tang

9433-2628

Acuity Sustainability Consulting Limited

Environmental Team Leader

Jacky Leung

2698-6833

ANewR Consulting Limited

Independent Environmental Checker

Nic Lam

2618-2831

1.4      Summary of Construction Works

1.4.1      Details of the major construction works undertaken in this reporting period are shown in Table 1.2 and Figure 1.3 below. The construction programme is presented in Appendix A.

Table 1.2 Summary of the Construction Works Undertaken during the Reporting Month

Location of works

Construction works undertaken

Remarks on progress

Portion A, B, C & D of the Project Site

·             Initial Joint Survey with Water Supplies Department

·             Completed

Portion F & G of the Project Site

·             Erection of fencing and gates

·             Completed and handed over to WSD/NTE on 15th Oct,2018

·             Site accommodation erection and internal fitting out

·             Completed and in operation

Portion J of the Project Site

(Figure 1.3)

·             Utilities checking and detection by Competent Person

·             In Progress

·             Ground Investigation of 17 no. of trial pits at Wan Po Road (CH. A3+50, 5+30, 13+70, 15+40, 16+30, 18+50, 19+00, 22+70, 41+10), Po Hong Road (CH. A44+80, 51+80, 63+60 and 69+60), Ling Hong Road (CH. A55+50 and 56+00), Po Shun Road (CH.A 54+30) and Wan Po Road (CH. A37+25).

·             Completed

·             Trial pit near Hong Kong Velodrome for identifying the existing utilities

·             In Progress

·             Open-trench between CH. A0+00 to 13+70

·             In Progress


Open Trench Area

Figure 1.3 Location of Major Construction Works Undertaken during the Reporting Month


1.5      Summary of Environmental Status

1.5.1      A summary of the valid permits, licences, and /or notifications on environmental protection for this Project is presented in Table 1.3

Table 1.3 Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations

Permit/ Licences/ Notification

Reference

Validity Period

Remarks

Variation of Environmental Permit

EP no.: EP-503/2015/A

Throughout the Contract

-

Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA)

Ref no.: 423775

Throughout the Contract

-

Chemical Waste Producer Registration

WPN: 5213-839-P3287-01

Throughout the Contract

-

Billing Account for Disposal of Construction Waste

A/C no.: 7029491

Throughout the Contract

-

1.5.2      The status for all environmental aspects is presented Table 1.4.

Table 1.4 Summary of Status for Key Environmental Aspects under the EM&A Manual

Parameters

Status

Noise

Baseline Monitoring

The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under VEP Condition 3.4

Impact Monitoring

On-going

Waste Management

Mitigation Measures in Waste Monitoring Plan

On-going

Landfill Gas

Impact Monitoring

On-going

Environmental Audit

Site Inspection

On-going

1.5.3      Other than the EM&A works by ET, regular environmental management meetings were conducted in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.

1.5.4      The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.

 

2.         Noise Monitoring

2.1      Monitoring Requirements

2.1.1      To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 – Creative Secondary School, (ii) NSR24 – PLK Laws Foundation College, and (iii) NSR31 – School of Continuing and Professional Studies – CUHK respectively.

2.1.2      In accordance with the EM&A Manual, baseline noise level at the noise monitoring stations were established as presented in the Baseline Monitoring Report. Impact noise monitoring will be conducted once per week in the form of 30-minutes measurements Leq, L10 and L90 levels recorded at each monitoring station between 0700 and 1900 hours on normal weekdays.

2.2      Noise Monitoring Parameters, Time, Frequency

2.2.1      Impact noise monitoring will be conducted weekly in the reporting period between 0700-1900 hours on normal weekdays. No construction works were carried out during 1900-0700 hours all days or any time on Sundays or general holidays during the reporting period.

2.2.2      Construction noise level measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. Table 2.1 summarizes the monitoring parameters, frequency and duration of the impact noise monitoring. The monitoring schedule is provided in Appendix C. Appendix C is intentionally left blank since no impact monitoring was conducted in the reporting month.

 Table 2.1 Noise Monitoring Parameters, Time, Frequency and Duration

Time

Frequency

Duration

Parameters

Daytime:

0700-1900 hours

Once per week

Continuously in

Leq 5min/Leq 30min (average of 6 consecutive Leq 5min)

Leq, L10 & L90

2.3      Noise Monitoring Locations

2.3.1      The monitoring locations should normally be made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) should be made to the free-field measurements.

2.3.2      According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.2 below.

Table 2.2 Noise Monitoring Location

NSR ID

Noise Sensitive Receivers

Monitoring Location

Position

NSR 4

Creative Secondary School

Roof Floor

1 m from facade

NSR 24

PLK Laws Foundation College

Pedestrian Road on Ground Floor

Free-field

NSR 31

School of Continuing and Professional Studies - CUHK

Roof Floor

1 m from facade

2.3.3      Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.


              

Figure 2.1 NSR4 Creative Secondary School


Figure 2.2 NSR24 PLK Laws Foundation College


Figure 2.3 NSR31 School of Continuing and Professional Studies - CUHK

2.4      Impact Monitoring Methodology

2.4.1      Integrated sound level meter shall be used for the noise monitoring.  The meter shall be in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency.  Measurements may be accepted as valid only if the calibration level before and after the noise measurements agree to within 1.0 dB(A). Calibration certificates of the instruments used are presented in Appendix D. Appendix D is intentionally left blank since no impact monitoring equipment was used in the reporting month.

2.4.2      Noise measurements shall not be made in the presence of fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

Table 2.3 Impact Noise Monitoring Equipment

Equipment

Brand and Model

Detection Limit

Sound Level Meter

Nti XL2

30-130 dB(A)

Sound Level Meter Calibrator

Rion NC-74

Nil

Pocket Wind Meter Anemometer

Kestrel 1000 Wind Meter

Nil

2.5      Action and Limit Levels

2.5.1      The Action/Limit Levels in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) “Noise from Construction Activities – Non-statutory Controls” and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [“EPD”] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 2.4.

Table 2.4 Action and Limit Levels for Noise

Time Period

Action

Limit (dB(A))

0700-1900 hours on normal weekdays

When one documented complaint is received from any one of the noise sensitive receivers

·         70 dB(A) for school and

·         65 dB(A) during examination period

Notes:

(a) Limits specified in the GW-TM and IND-TM for construction and operation noise, respectively.

2.5.2      If exceedances were found during noise monitoring. The actions in accordance with the Event and Action Plan shall be carried out according to Appendix E.

2.6      Monitoring Results and Observations

2.6.1      Noise monitoring data shall be recovered in real-time as it is a manned-event with data display from the sound level meters.

2.6.2      Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out at all the designated monitoring stations when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations. No impact monitoring for noise impact was conducted in the reporting period due to the over distant monitoring station from the works location, where they were farther than 1 km from the closest monitoring station NSR4 to the works location.

2.6.3      Detailed monitoring results are presented in Appendix F. Appendix F is intentionally left blank since there is no impact monitoring for noise impact in this reporting month.


 

3.         Waste management

3.1      The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 3.1. Details of cumulative waste management data are presented as a waste flow table in Appendix G.

 

Table 3.1 Quantities of waste generated from the Project

Reporting period

Quantity

Inert C&D Materials

(in ‘000m3)

Chemical Waste

(in ‘000kg)

Non-inert C&D Materials

 Others, e.g. General Refuse disposed at Landfill

(in ‘000m3)

Recycled materials

Paper/card board

(in ‘000kg)

Plastics

(in ‘000kg)

Metals

(in ‘000kg)

Dec-18

0.364

0.000

0.046

0.083

0.000

0.000

 


4.         Landfill gas monitoring

4.1      Monitoring Requirement

4.1.1      In accordance with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter fresh water mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.

4.2      Monitoring Location

4.2.1      Monitoring of oxygen, methane, carbon dioxide and barometric pressure was performed for excavations at 1m depth or more within the consultation Zone. In this reporting period, 144 times of monitoring was recorded.

4.2.2      During construction of works within the consultation zones, excavations of 1m depth or more was monitored:

·             At the ground surface before excavation commences;

·             Immediately before any worker enters the excavation;

·             At the beginning of each working day for the entire period the excavation remains open; and

·             Periodically through the working day whilst workers are in the excavation.

For excavations between 300mm and 1m deep, measurements should be carried out:

·             Directly after the excavation has been completed; and

·             Periodically whilst the excavation remains open.

4.2.3      The area required to be monitored for landfill gas in the reporting period are shown in Figure 4.1 to Figure 4.3.


SK025-EM&A mth report_2018

Figure 4.1 Monitoring Location - CH.A 1+50


SK025-EM&A mth report_2018

Figure 4.2 Monitoring Location -CH.A 7+20


SK025-EM&A mth report_2018

Figure4.3 Monitoring Location – CH.A 13+70

 

4.3      Monitoring Parameters

4.3.1      LFG monitoring was carried out to identify any migration between the landfill and the Project and to ensure the safety of the construction, operation and maintenance personnel working on-site, visitors and any other person within the Project area.

4.3.2      The following parameters were monitored:

·             Methane.

·             Oxygen.

·             Carbon Dioxide.

·             Barometric Pressure.

 

4.4      Action and Limit Level

4.4.1      Action and Limit Level is provided in Table 4.1.

Table 4.1 Action and Limit Level for Landfill Gas Monitoring Equipment

Parameters

Action Level

Limit Level

Oxygen (O2)

<19% O2

<19% O2

Methane (CH4)

>10% LEL

>80% LEL

Carbon Dioxide (CO2)

>0.5% CO2

>1.5% CO2

 

4.5      Monitoring Equipment

4.5.1      Landfill Gas monitoring was carried out using intrinsically-safe, portable multi-gas monitoring instruments.  The gas monitoring equipment is:

·             Comply with the Landfill Gas Hazard Assessment Guidance Note as intrinsically safe;

·             Capable of continuous barometric pressure and gas pressure measurements;

·             Normally operate in diffusion mode unless required for spot sampling, when it should be capable of operating by means of an aspirator or pump;

·             Have low battery, fault and over range indication incorporated;

·             Store monitoring data, and shall be capable of being down-loaded directly;

·             Measure in the following ranges:

methane

0-100% Lower Explosion Limit (LEL) and 0-100% v/v;

oxygen

0-25% v/v;

carbon dioxide

0-100% v/v; and

barometric pressure

mBar (absolute)

·              alarm (both audibly and visually) in the event that the concentrations of the following are exceeded:

methane

>10% LEL;

oxygen

>0.5% by volume; and

carbon dioxide

<19% by volume

barometric pressure

mBar (absolute)

 

4.5.2      Monitoring Equipment used in the reporting period are summarised in Table 4.2. The Landfill Gas monitoring equipment calibration certificate is presented in Appendix H.

Table 4.2 Landfill Gas Monitoring Equipment

Equipment

Brand and Model

Calibration Expiry Date

Portable Gas Detector

QRAE3

17-Oct-2019

Portable Gas Detector

 Industrial Scientific Corporation M40

28- Augt-2019

 

4.6      Monitoring Results

4.6.1      In the reporting period, construction works within the consultation zones, excavations of 1m depth or more was monitored. Landfill gas monitoring was carried out by the Registered Safety Officer by the Contractor at the excavation locations for 144 times. All the measured results were presented in Appendix I and within the Action and Limit Levels.

 


 

5.         Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions

5.1      The Environmental Complaint Handling Procedure is shown in below Figure 5.1:

complaint handling

Figure 5.1 Environmental Complaint Handling Procedure


 

5.2      No noise monitoring was conducted during the reporting period since there are no projected-related construction activities undertaken within a radius of 300m from the monitoring locations. No project-related exceedance of the Action Level was recorded during the reporting period.

5.3      No notification of summons and prosecution was received in the reporting period.

5.4      Statistics on complaints and regulatory compliance are summarized in Appendix J.


 

6.         EM&A Site Inspection

6.1      Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out on 5,11,18,25 and 30 October 2018 at the site portions list in Table 6.1 below.

Table 6.1 Site Inspection Record

Date

Inspected Site Portion

Time

5,11,18,25 and 30 October 2018

Portion J, F & G of the Site

10:00am - 11:00am

6.2      One joint site inspection with IEC was carried out on 30 October, 2018.

6.3      Minor deficiencies were observed during weekly site inspection. Key observations during the site inspections are summarized in Table 6.2.

Table 6.2 Site Observations

6.4      No observations was found during environmental site inspections in the reporting period.

6.5      According to the EIA Study Report, Environmental Permit, contract documents and EM&A Manual, the mitigation measures detailed in the documents are implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix B.

6.6      Site inspection proforma of the reporting period is provided in Appendix K.


 

7.         Future Key Issues

7.1      Key works anticipated in the next reporting period for the Project will include the following:

·            Trial pit works to check with the existing utilities

·            Trial pits excavation at HK Velodrome

·            3 nos. of open-trench between CH. A0+00 to 13+70.

7.2      The major environmental impacts brought by the above construction works will include:

·            Construction dust and noise generation from trial pits works, trench excavating works

·            Waste generation from construction activities

7.3      The key environmental mitigation measures for the Project in the coming reporting period associated with the above construction works will include:

·            Dust suppression by regular wetting and water spraying for trial pits works, trench excavation

·            Reduction of noise from equipment and machinery on-site

·            Sorting and storage of general refuse and construction waste

7.4      The proactive environmental protection proforma for the next reporting month is listed in Appendix L.

7.5      The impact monitoring schedule for the next reporting month is attached in Appendix M. Appendix M is intentionally left blank since no impact monitoring will be conducted in the next reporting month.

7.6      Referring to EM&A Manual Section 4.1.2, the impact noise monitoring should be carried out at all the designated monitoring stations when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations.No noise monitoring was scheduled in the next reporting period due to the over distant monitoring station from the works location.

 


 

8.         Conclusion and Recommendations

8.1      This 3rd monthly Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken during the period from 1 October 2018 to 31 October 2018 in accordance with the EM&A Manual and the requirement under EP-503/2015/A.

8.2      No noise monitoring was conducted during the reporting period due to the over distant monitoring station from the works location. No project-related exceedance of the Action Level was recorded during the reporting period.

8.3      Weekly environmental site inspection was conducted during the reporting period. Minor deficiencies were observed during site inspection and were rectified. The environmental performance of the Project was therefore considered satisfactory.

8.4      According to the environmental site inspections performed in the reporting month, the Contractor is reminded to pay attention on maintaining site tidiness and proper materials storage.

8.5      No environmental complaint was received in the reporting period.

8.6      No notification of summons or prosecution was received since commencement of the Contract.

8.7      The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 


 

 

 

 

 

 

 

 

 

 

Appendix A

 

Construction Programme


 




 

 

 

 

 

 

 

 

 

Appendix B

 

Summary of Implementation Status of Environmental Mitigation


 

EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation

status

Relevant Legislation & Guidelines

D

C

O

Air Quality

 

S4.8.1

Impervious dust screen or sheeting will be provided to enclose scaffolding from the ground floor level of building for construction of superstructure of the new buildings.

Land site/ During Construction

Contractor(s)

 

ü

 

 

Air Pollution Control (Construction Dust)

S4.8.1

Impervious sheet will be provided for skip hoist for material transport.

Land site/ During Construction, particularly dry season

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

The area where dusty work takes place should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after dusty activities as far as practicable.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

All dusty materials should be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Dropping heights for excavated materials should be controlled to a practical height to minimise the fugitive dust arising from unloading.

Land site/ During Construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

During transportation by truck, materials should not be loaded to a level higher than the side and tail boards, and should be dampened or covered before transport.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Wheel washing device should be provided at the exits of the work sites. Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty material from its body and wheels as far as practicable.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Road sections between vehicle-wash areas and vehicular entrance will be paved.

Land site/ During Construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site boundary.

Land site/ During construction

Contractor(s)

ü

ü

 

Implemented

 

S4.8.1

Haul roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road surface wet at all times.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Temporary stockpiles of dusty materials will be either covered entirely by impervious sheets or sprayed with water to maintain the entire surface wet all the time.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Stockpiles of more than 20 bags of cement, dry pulverised fuel ash and dusty construction materials will be covered entirely by impervious sheeting sheltered on top and 3-sides.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

All exposed areas will be kept wet always to minimise dust emission.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

 

S4.8.1

Ultra-low-sulphur diesel (ULSD) will be used for all construction plant on-site, as defined as diesel fuel containing not more than 0.005% sulphur by weight) as stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites.

Land site/ During construction/ During Operation

Contractor(s)

 

ü

ü

Implemented

Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on

Environmental Management on Construction Sites

S4.8.1

The engine of the construction equipment during idling will be switched off.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

 

S4.8.1

Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented.  The control measures recommended in the Guidance Note on a Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

Guidance Note on a Best

S4.8.1

Regular maintenance of construction equipment deployed on-site will be conducted to prevent black smoke emission.

Land site/ During construction

Contractor(s)

 

ü

 

N/A

 

S4.10

To ensure proper implementation of the recommended dust mitigation measures and good construction site practices during the construction phase, environmental site audits on weekly basis is recommended throughout the construction period.

Land site/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

 

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation

status

Relevant Legislation & Guidelines

D

C

O

 

Noise

S5.7

Only well-maintained plant will be operated on-site and plant will be serviced regularly during the construction phase.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Silencers or mufflers on construction equipment will be utilised and will be properly maintained during the construction phase.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Mobile plant, if any, will be sited as far away from NSRs as possible.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down to a minimum.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Plants known to emit noise strongly in one direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Material stockpiles and other structures will be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Use of Quite Powered Mechanical Equipment (QPME).

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Movable noise barriers of 3m in height with skid footing should be used and located within a few metres of stationary plant and mobile plant such that the line of sight to the NSR is blocked by the barriers. The length of the barrier should be at least five times greater than its height. The noise barrier material should have a superficial surface density of at least 7 kg m-2 and have no openings or gaps.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

The noise insulating sheet should be deployed such that there would be no opening or gaps on the joints.

Noise control/ During construction

Contractor(s)

 

ü

 

N/A

A Practical Guide for the Reduction of Noise from Construction Works,

S5.7

Construction activities (e.g. excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence, such that items of PME proposed for these activities will not be operated simultaneously.

Noise control/ During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works

S5.7

PMEs will not be used at the works areas near educational institutions with residual impact (ie the “influence area” within a radius of 40m) during school hours in order to reduce impact to the educational institutions.

Noise control / During construction

Contractor(s)

 

ü

 

Implemented

A Practical Guide for the Reduction of Noise from Construction Works

S5.7

Noise enclosures or acoustic sheds would be used to cover stationary PME such as generators.

Portable/Movable noise enclosure made of material with superficial surface density of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

 

Implemented

 

S5.9

Sawcutting pavement, breaking up of pavement, excavation /shoring, pipe laying, backfilling, reinstatement (concrete) and pipe jacking shall be scheduled outside the examination period.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

 

N/A

 

S5.9

In view the duration of noise exceedance at Creative Secondary School, PLK Laws Foundation College,  TKO Kei Tak Primary School and School of Continuing and Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools shall be scheduled during long school holidays (eg summer holiday, Easter holiday or Christmas holiday,

etc) as far as practicable. Scheduling the construction work for the four schools.

Noise control/ Pre- construction/ During construction

Contractor(s)

ü

ü

 

Implemented

 

S5.10

A noise monitoring programme shall be implemented for the construction phase.

Designated monitoring stations as defined in EM&A Manual/During construction phase

Environmental Team (ET)

 

ü

 

Implemented

 

S5.10

The effectiveness of on-site control measures could also be evaluated through the regular site audits.

All facilities/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

-

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation

status

Relevant Legislation & Guidelines

D

C

O

Water Quality

S6.9

Dredged marine sediment will be disposed of in a gazetted marine disposal area in accordance with marine dumping permit conditions of the Dumping at Sea Ordinance (DASO).

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

Dumping at Sea Ordinance (DASO)

S6.9

Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

All vessels must have a clean ballast system.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

No discharge of sewage/grey wastewater should be allowed. Waste water from potentially contaminated area on working vessels should be minimized and collected.   These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

No soil waste is allowed to be disposed overboard.

Marine Dredging/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Silt removal facilities such as silt traps or  sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO.   The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94.   All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms.   Deposited silt and grit will be removed regularly.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

ProPECC PN 1/94 TM

Standard under the WPCO

S6.9

Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Appropriate surface drainage will be designed and provided where necessary.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

ProPECC PN 1/94

S6.9

Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the storm water drainage system after accidental spillages.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9

Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any, will be adequately designed for the controlled release of storm flows.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9

The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

N/A

-

S6.9

Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment.

Land site & drainage/ During construction

Contractor(s)

 

ü

 

Implemented

-

S6.9 and S6.12

The sterilization water should be dechlorinated with total residual chlorine (TRC) level below 1 mg/L before discharge to public sewer. In situ testing of TRC should also be conducted for the discharge of chlorinated water for pipeline disinfection to ensure sufficient dechlorination before discharge to public sewer.

Sterilization of water mains prior to commissioning

Contractor(s)

 

ü

ü

N/A

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters

S6.9

The cleaning and flushing water should also be treated and desilted to the relevant discharge requirement stipulated in TM-DSS before discharging.

Sterilization of water mains prior to commissioning

Contractor(s)

 

ü

ü

N/A

Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters

S6.9

Site drainage should be well maintained and good construction practices should be observed to ensure that oil, fuels, solvents and other chemicals are managed, stored and handled properly and do not enter the nearby water streams.

Land site & drainage/ During construction/ During operation

Contractor(s)

 

ü

ü

Implemented

-

S6.12

Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the standard site practice and mitigation measures as proposed to reduce potential impacts to water quality.

During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

-

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

Waste Management

S8.5

Nomination of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes generated at the site.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Training of site personnel in proper waste management and chemical handling procedures. Training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning of the construction works.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Provision of sufficient waste disposal points and regular collection for disposal.

All area/ During construction/ During operation

Contractor(s)

 

ü

ü

Implemented

DEVB TC(W) No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness.

S8.5

Appropriate measures to reduce windblown litter and dust transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 8/2010,

Enhanced Specification for Site Cleanliness and Tidiness.

S8.5

A waste management plan (WMP) as stated in the ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites”   for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP).   The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior to implementation.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

ETWB TC(W) No. 19/2005,

Environmental Management on Construction Sites

S8.5

Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical Wastes published under the Waste Disposal Ordinance (Cap 354),

Section 35

S8.5

Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

Waste Disposal Ordinance (Cap 354)

S8.5

A recording system for the amount of wastes generated/ recycled and disposal sites.   The trip- ticket system will be included as one of the contractual requirements and implemented by the contractor(s).

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of material and their proper disposal.

Land site/ During construction/ During operation

Contractor(s)

 

ü

 

Implemented

WBTC 32/92, The Use of Tropical Hard Wood on Construction Site

S8.5

Encourage collection of aluminium cans and waste paper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

ETWB TCW No. 33/2002,

Management of Construction and Demolition Material Including Rock

S8.5

Any unused chemicals and those with remaining functional capacity will be recycled as far as possible.

Land site/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Use of reusable non-timber formwork to reduce the amount of C&D materials.

All areas/ During construction

Contractor(s)

 

ü

 

N/A

WBTC 32/92, The Use of Tropical Hard Wood on Construction Site

S8.5

Prior to disposal of construction waste, wood, steel and other metals will be separated to the extent practical, for re-use and/or recycling to reduce the quantity of waste to be disposed of to landfill.

All areas/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

Proper storage and site practices to reduce the potential for damage or contamination of construction materials.

All areas/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

Plan and stock construction materials carefully to reduce amount of waste generated and avoid unnecessary generation of waste.

All areas/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval.   The approved detailed sampling and chemical testing will be carried out prior to the commencement of the dredging activities to confirm the sediment disposal method.

Marine works/ During construction

Contractor(s)

 

ü

 

N/A

ETWB TC(W) No. 34/2002

and Dumping at Sea Ordinance (DASO)

S8.5

The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the Specification of the Contract Documents.

Marine works/ During construction

WSD/ Contractor(s)

 

ü

 

Implemented

ETWB TC(W) No. 34/2002 and Dumping at Sea Ordinance (DASO)

S8.5

The contractor will open a billing account with EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

Cap 354N Waste Disposal (Charges for Disposal of Construction Waste) Regulation

S8.5

A trip-ticket system will be established in accordance with DEVB TC(W) No. 6/2010 to monitor the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and to control fly-tipping.

Contract mobilisation/ During construction

Contractor(s)

 

ü

 

Implemented

DEVB TC(W) No. 6/2010,

Trip Ticket System for Disposal of Construction & Demolition Materials

S8.5

The project proponent will also conduct regular inspection of the waste management measures implemented on site as described in the Waste Management Plan.

All area/ During construction

Contractor(s)/ Environmental Team (ET) & Independent Environmental Checker (IEC)

 

ü

 

Implemented

ETWB TC(W) No. 19/2005,

Environmental Management on Construction Sites

S8.5

A recording system (similar to summary table as shown in Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005) for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established during the construction phase.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Annex 5 and Annex 6 of Appendix G of ETWB TC(W) No. 19/2005

S8.5

Inert C&D materials (public fill) will be reused within the Project as far as practicable.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse or recycling of materials and their proper disposal.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable.

All area/ During construction

Contractor(s)

 

ü

 

N/A

-

S8.5

To reduce the potential dust and water quality impacts of site formation works, C&D materials will be wetted as quickly as possible to the extent practice after filling.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Air Pollution Control (Construction Dust) Regulation (Cap 311R); WPCO (Cap 358)

S8.5

Open stockpiles of excavated/ fill materials or construction wastes on-site should be covered with tarpaulin or similar fabric.

Land site/ During Construction, particularly dry season

Contractor(s)

 

ü

 

N/A

Air Pollution Control (Construction Dust) Regulation (Cap 311R)

S8.5

Chemical waste container shall be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Chemical waste container shall have a capacity of less than 450 L unless the specifications have been approved by the EPD.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

A label in English and Chinese shall be displayed on the chemical container in accordance with instructions prescribed in Schedule 2 of the Regulations.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall be enclosed on at least 3 sides.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall have adequate ventilation.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary).

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Storage areas for chemical waste shall be arranged so that incompatible materials are appropriately separated.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

General refuse will be stored in enclosed bins or compaction units separately from construction and chemical wastes.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

Waste Disposal (Chemical Waste) (General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

S8.5

Adequate number of waste containers will be provided to avoid over-spillage of waste.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

DEVB TC(W) No. 8/2010

Enhanced Specification for Site Cleanliness and Tidiness.

S8.5

A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimise odour, pest and litter impacts.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

N/A

-

S8.5

Recycling bins will be provided at strategic locations within the Site to facilitate recovery of recyclable materials (including aluminium can, waste paper, glass bottles and plastic bottles) from the Site.

Materials recovered will be sold for recycling.

All area/ During construction/ During operation

Contractor(s)/ WSD

 

ü

ü

Implemented

-

S8.5

To avoid any odour and litter impact, accurate number of portable toilets will be provided for workers on-site.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S8.5

The burning of refuse on construction sites is prohibited by law.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

Air Pollution Control Ordinance (Cap 311)

S8.7

To facilitate monitoring and control over the contractors’ performance on waste management, a waste inspection and audit programme will be implemented throughout the construction phase.

All facilities/ During construction

ET/ IEC

 

ü

 

Implemented

-

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Ecology

S9.7

For slope mitigation works within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the exact locations of the flexible barrier foundation plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical.   A detailed specification describing the exact locations of the flexible barrier foundation plates, soil nails and rock dowels will be prepared to illustrate how the setback distance from existing trees would be implemented for tree avoidance.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

Implemented

-

S9.7

Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

 

S9.7

The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable.   All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a minimum 1.5m in a radius away from these individuals.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

Implemented

-

S9.7 and 9.10

At the detailed design stage prior to the commencement of the slope mitigation works, a vegetation survey shall be carried out at the slope mitigation areas within the Clear Water Bay Country Park to assess the condition and identify the location of each individual of Marsdenia lachnostoma and other flora species of conservation interest that may be directly affected by the construction works.

Slope mitigation works area/ During detailed design/ During construction

Contractor(s)

ü

ü

 

Implemented

-

S9.7

Temporary fencing will be installed to fence off the concerned species either in groups of individually within the works area and in the close proximity to prevent from being damaged and disturbed during construction. A sign identifying the site shall be attached to the fence and flagging tape shall be attached to the individuals to visualize their locations.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7 and S9.10

A specification for fencing and demarcating individuals of Marsdenai lachnostoma (or other flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Induction training shall also be provided to all site personnel in order to brief them on this flora of conservation interest including the locations and their importance.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

The resident site supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close proximity.

Slope mitigation works area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Erect fences along the boundary of the works area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Regularly check the work site boundaries to ensure that they are not breached and that damage does not occur to surrounding areas.

All area/ During construction

Contractor(s)/ Environmental Team (ET)

 

ü

 

Implemented

-

S9.7

Avoid any damage and disturbance, particularly those caused by filling and illegal dumping, to the surrounding habitats through proper management of waste disposal.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Reinstate temporarily affected areas, particularly the habitats of plantation and shrubland-grassland immediately after completion of construction works, through on-site tree/shrub planting. The tree/shrub species will be chosen with reference to those in the surrounding area.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

S9.7

Affected habitats within the Clear Water Bay Country Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub seedlings where practical upon completion of the slope mitigation works.

All area/ During construction

Contractor(s)

 

ü

 

Implemented

-

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Landscape & Visual

S11.10 & 11.11

The construction area and area allowed for temporary structures, such as the contractor’s office, will be minimized to a practical minimum.   (MM1)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

At the detailed design stage, the design team will seek to minimize the landscape footprint of the Project and above ground facilities, while satisfying all other requirements. (MM2)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

Design principles will be adopted to take into account the surrounding area, particularly Clear Water Bay Country Park behind and the nearby waterfront, with due consideration given to:

-  green roofs where practical (ie without equipment on the roof);

-  roadside planting;

-  aesthetic treatment of all structures;

-  vertical greening;

screen planting along application site; and

- landscape enhancement with amenity planting where practical including planting along the edge (site boundary) fence with native shrubs where feasible,

-  to reduce their visual impact and blend them into the surrounding landscape.   (MM3)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

S11.10 & 11.11

All trees within the Project Site or the potential slope mitigation works area will be carefully protected during construction according to DEVB TCW No.

10/2013 Tree Preservation (MM4)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

ETWB TCW No. 3/2006 -

Tree Preservation.

S11.10 & 11.11

No tree within the Country Park will be felled.    Trees within the Site unavoidably affected by the works will be transplanted where necessary and practical.   For trees that need to be felled, compensatory planting will be provided to the satisfaction of relevant Government departments.

A compensatory tree planting proposal including locations of tree compensation will be submitted to seek relevant government department’s approval, in accordance with DEVB TC(W) No. 10/2013.   (MM5)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

DEVB TC(W) No. 10/2013

S11.10 & 11.11

Any slope mitigation works necessary to address natural terrain hazards, will be minimized to minimize any potential environmental impact to the Country Park e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the best planting matrix with native species will be established, with the aim of resembling the existing vegetation.                          (MM6)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

 

S11.10 & 11.11

Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid or reduce any potential environmental impacts to as low as reasonably practicable (ALARP). The intake and outfall structures (e.g. intake openings and diffuser heads) will be prefabricated and transferred to site for installation.   (MM7)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

N/A

 

S11.10 & 11.11

All night-time lighting will be reduced to a practical minimum both in terms of number of level and will be hooded and directional. (MM8)units and lux level and will be hooded and directional. (MM8)

All area/ Detailed design/ During construction/ During operation

WSD/ Contractor(s)

ü

ü

ü

Implemented

-

Note:  D – Design stage  C – Construction  O – Operation


EIA Reference

Recommended Environmental Protection Measures/ Mitigation Measures

Objectives of the recommended measures & main concerns to address

Implementation Agent

Implementation Stage

Implementation Status

Relevant Legislation & Guidelines

D

C

O

 

Landfill Gas Hazard

S12.7

During all works, safety procedures should be implemented to minimise the risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with contaminated soil and groundwater.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

-

S12.7

During trenching and excavation as well as creation of confined spaces at near to or below ground level, precautions should be clearly laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available and used when entering confined spaces or trenches deeper than 1 metre.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

The Contractor should make the workers are aware of potential hazards of working in confined spaces (any chamber, manhole or culvert which is large enough to permit access to personnel).   Such work in confined spaces is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and Industrial Undertakings Ordinance.

Following the Safety Guide to Working in Confined Spaces ensures compliance with the above regulations.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the site throughout the works, in particular, when works are undertaken below grade.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

All personnel who work on site and all visitors to the site should be made aware of the possibility of  ignition of gas in the vicinity of the works, the possible presence of contaminated water and the need to avoid physical contact with it.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during pipe jacking) and any confined spaces through the use of an intrinsically safe portable instrument, appropriately calibrated and capable of measuring the concentrations of methane. carbon dioxide and oxygen.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

Monitoring frequency and areas to be monitored should be specified prior to commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person.   All measurements should be recorded and documented.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

Proceed drilling with adequate care and precautions against the potential hazards which may be encountered.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Prior to the commencement of the site works, the drilling contractor should devise a 'method-of- working' statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of operatives, normal method of operations, emergency procedures, supervisors responsibilities, storage and use of safety equipment, safety procedures and signs, barriers and guarding).   The site supervisor and all operatives must be familiar with this statement.

All area/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

S12.7

Where below ground service entries are necessary to the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II), the entry point should be sealed to prevent gas entry.   In addition, any below grade cable trenches entering the Incoming Switchgear Room and 132 kV Substation can become the pathway for landfill gas and hence grilled metal covers should be used.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

It is recommended regular landfill gas monitoring should be carried out at the Incoming Switchgear Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the first year of operation. If the monitoring results show no sign of landfill gas migration, reduce the monitoring frequency to once every six months.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

The manholes and utility pits within the Project Site and along the fresh water mains. Each manhole/ utility pit should be monitored with two measurements (at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and peak reading should be recorded at each manhole/ utility pit and for each measurement.   The need for venting the manhole/ utility pit and further monitoring will be reviewed after the initial monitoring.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

N/A

 

S12.7

All construction, operation and maintenance personnel working on-site as well as visitors should be made aware of the hazards of landfill gas and its possible presence on-site. This should be achieved through a combination of posting warning signs in prominent places and also by access to detailed information on landfill gas hazards and the designs and procedural means by which these hazards are being minimised

on-site.

All area/ Detailed design/ During construction/ During operation

Contractor(s)

ü

ü

ü

Implemented

 

Note:  D – Design stage  C – Construction  O – Operation


 

 

 

 

 

 

 

 

 

 

 

 

Appendix C

 

Impact Monitoring Schedule of the Reporting Month


 

 

 

 

 

 

 

 

 

 

(Blank)

 

 

 

 

 

 

 

 

 

 

Appendix D

 

Noise Monitoring Equipment Calibration Certificate


 

 

 

 

 

 

 

 

 

 

(Blank)

 

 

 

 

 

 

 

 

 

Appendix E

 

Date

Environmental Observations

Follow-up Status

5-Oct 2018

No observations

-

11-Oct 2018

No observations

-

18-Oct 2018

No observations

-

25-Oct 2018

No observations

-

30-Oct 2018

No observations

-

 

 

Event/Action Plan for Noise Exceedance



 

 

 

 

 

 

 

 

 

 

 

 

 

Appendix F

 

Noise Monitoring Data


 

 

 

 

 

 

 

 

 

 

(Blank)

 

 

 

Appendix G

 

Waste Flow Table


Monthly Summary Waste Flow Table

Name of Department:       WSD       Contract No. / Works Order No.: __13/WSD/16__

Monthly Summary Waste Flow Table for   October 2018       

 

Month

Actual Quantities of Inert Construction Waste Generated Monthly

Total Quantity Generated

Hard Rock and Large Broken Concrete

(see Note 5)

Reused in the Contract

Reused in other Projects

Disposed of as Public Fill

Imported Fill

(see Note 4)

(in ‘000m3)

(in ‘000m3)

(in ‘000m3)

(in ‘000m3)

(in ‘000m3)

(in ‘000m3)

Jan 2018

0.000

0.000

0.000

0.000

0.000

0.000

Feb 2018

0.000

0.000

0.000

0.000

0.000

0.000

Mar 2018

0.011

0.000

0.000

0.000

0.011

0.000

Apr 2018

0.011

0.000

0.000

0.000

0.011

0.000

May 2018

0.010

0.000

0.000

0.000

0.010

0.000

Jun 2018

0.003

0.000

0.000

0.000

0.003

0.000

Sub-total

0.035

0.000

0.000

0.000

0.035

0.000

Jul 2018

0.048

0.000

0.000

0.000

0.048

0.000

Aug 2018

0.004

0.003

0.000

0.000

0.004

0.000

Sep 2018

0.231

0.014

0.000

0.000

0.231

0.000

Oct 2018

0.364

0.025

0.000

0.000

0.364

0.089

Nov 2018

 

 

 

 

 

 

Dec 2018

 

 

 

 

 

 

Total

0.682

0.042

0.000

0.000

0.682

0.089


 

Month

Actual Quantities of Non-inert Construction Waste Generated Monthly

Metals

Paper/ cardboard packaging

Plastics

(see Note 2)

Chemical Waste

 Others, e.g. General Refuse disposed at Landfill

(in ‘000kg)

(in ‘000kg)

(in ‘000kg)

(in ‘000kg)

(in ‘000m3)

Jan 2018

0.000

0.000

0.000

0.000

0.000

Feb 2018

0.000

0.000

0.000

0.000

0.000

Mar 2018

0.000

0.000

0.000

0.000

0.000

Apr 2018

0.000

0.014

0.000

0.000

0.000

May 2018

0.000

0.000

0.000

0.000

0.003

Jun 2018

0.000

0.032

0.000

0.000

0.000

Sub-total

0.000

0.046

0.000

0.000

0.003

Jul 2018

0.000

0.038

0.000

0.000

0.030

Aug 2018

0.000

0.042

0.000

0.000

0.000

Sep 2018

0.000

0.069

0.000

0.000

0.046

Oct 2018

0.000

0.083

0.000

0.000

0.046

Nov 2018

 

 

 

 

 

Dec 2018

 

 

 

 

 

Total

0.000

0.278

0.000

0.000

0.125

Notes:

1.     The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site.

2.     Plastic refer to plastic bottles/containers, plastic sheets/foam from packaging materials.

3.     Broken concrete for recycling into aggregate.

4.     Sources and types of Imported Fill in the reporting period: (i) K.Wah Quarry Company Limited (Soil): 89.474m(170.00 tonne)

 

5.     The amount of Hard Rock and Large Broken Concrete are disposed to public fill, the breakdown of C&D materials disposed to public fill is shown as below:

Type of C&D Materials

 

Description of C&D Materials

 

C&D Waste Disposed

(Volume)

(m3)

Inert

Bentonite

--

Broken Concrete

20.15

Broken Rock

4.90

Mixed Construction Waste (>50% inert)

--

Building Debris

5.05

Mixed Rock and Soil

237.95

Reclaimed Asphalt Pavement

90.95

Slurry

--

Soil

4.85

TOTAL =

363.85

Non-inert

--

45.65


 

 

 

 

 

 

 

 

 

 

Appendix H

 

Landfill Gas Monitoring Equipment Calibration Certificate


 

 

 

 

 

 

Appendix I

 

Landfill Gas Monitoring Data

 

Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018Landfill gas monitoring 2018

 

 

 

 

 

 

Appendix J

 

Complaint Log and Regulatory Compliance Proforma

 


 

 

Statistical Summary of Environmental Complaints

 

 

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

1 Oct 2018-

 

31 Oct 2018

 

0

 

0

 

N/A

 

 

 

 

Statistical Summary of Environmental Summons

 

 

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Details

1 Oct 2018-

 

31 Oct 2018

 

0

 

0

 

N/A

 

 

 

Statistical Summary of Environmental Prosecution

 

 

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Details

1 Oct 2018-

 

31 Oct 2018

 

0

 

0

 

N/A

 

 

 

 


 

 

 

 

 

 

 

 

 

 

 

Appendix K

 

Site Inspection Proforma


 

all1all2all3all4all5all6all7all8all9all10all11all12all13all14all15all16all17all18all19all20all21all22all23all24all25all26all27all28all29all30

 

 

 

 

 

 

Appendix L

 

Proactive Environmental Protection Proforma


 

Proactive Environmental Protection for the Next Reporting Month

 

 

Reporting Period

Activity

Major Environmental Impact

Environmental Mitigation Measure

1 Nov 2018 -

30 Nov 2018

-    Trial pit works to check with the existing utilities and for alternative alignment at HK Velodrome

-    Construction dust and noise generation

-    Dust suppression by regular wetting and water spraying

-    Reduction of noise from equipment and machinery on-site

-    CH. A0+00 to 13+70: open trench

-    Construction dust and noise generation from open trenching

-    Waste generation from construction activities

-    Dust suppression by regular wetting and water spraying in the open trench area

-    Reduction of noise from equipment and machinery on-site

-    Sorting and storage of general refuse and construction waste


 

 

 

 

 

 

 

 

 

Appendix M

 

Impact Monitoring Schedule of Next Reporting Month


 

 

 

 

 

 

 

 

 

 

(Blank)